uae’s first nuclear plant is 75 per cent complete
Last Updated : GMT 06:49:16
Arab Today, arab today
Arab Today, arab today
Last Updated : GMT 06:49:16
Arab Today, arab today

UAE’s first nuclear plant is 75 per cent complete

Arab Today, arab today

Arab Today, arab today UAE’s first nuclear plant is 75 per cent complete

Officials of the Emirates Nuclear Energy Corporation say that Barakah plant’s construction is on schedule, with Units 3 and 4 ahead of schedule.
Abu Dhabi - Arab Today

Construction work on the UAE’s first nuclear power plant is now more than 75 per cent complete, the state-run Emirates Nuclear Energy Corporation (ENEC) said on Saturday.

Rising from the desert sands in the eastern part of Abu Dhabi emirate, the Barakah plant is set to come online by 2020.

The nuclear plant is expected to provide for a quarter of the UAE’s electricity needs — and save up to 12 million tonnes in carbon emissions every year.

Construction began in 2012 by a consortium of builders led by the South Korean power giant Korean Electric Power Corporation (KEPCO).

Work on the four-reactor plant is divided into four units, all of which are being built simultaneously.

On Units 3 and 4, which have the most distant construction deadlines, work is more than 50 per cent done. The roof on Unit 3’s reactor vessel — which houses the reactor core — has recently been installed. Last July, the unit’s reactor vessel was installed.

In Unit 4, the turbine generator operating deck and reactor containment liner plates have been set in place.

Officials of the ENEC say that Barakah plant’s construction is on schedule, with Units 3 and 4 ahead of schedule.

“The latest successful achievement of these milestones for Units 3 and 4 is a result of many months of hard work by all those involved,” said ENEC chief Mohammad Al Hammadi.

“I am proud of our teams whose commitment and dedication is a key factor in the continued successful construction of the world’s largest nuclear new build construction site.”

The nuclear energy project will help create high-value job opportunities and help spark the “emergence of a new sophisticated industrial sector” to support the plant, Al Hammadi said.

Once completed, officials expect the plant to deliver safe, clean, reliable and efficient nuclear energy to the UAE grid.

source : gulfnews

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

uae’s first nuclear plant is 75 per cent complete uae’s first nuclear plant is 75 per cent complete

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

uae’s first nuclear plant is 75 per cent complete uae’s first nuclear plant is 75 per cent complete

 



GMT 03:23 2017 Monday ,17 April

Oman to take part in Rabat meeting

GMT 14:43 2017 Tuesday ,03 October

EU parliament to denounce lack of progress on Brexit

GMT 02:12 2017 Wednesday ,27 December

Lactalis Baby Milk Contamination

GMT 04:34 2017 Thursday ,21 December

Royal row as body of king who aided Mussolini returns

GMT 01:48 2017 Wednesday ,22 November

ERC provides aid relief in Hadramaut districts

GMT 09:06 2017 Thursday ,09 March

Digital publishing pays off for Axel Springer

GMT 13:03 2016 Wednesday ,21 December

Fila partners with Mountain dews green label exclusives

GMT 09:15 2017 Thursday ,09 November

Government Treasury Bills issue 1677 fully subscribed
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday