Thirst for energy leads to massive dig in the desert

Arab Today, arab today

Arab Today, arab today Thirst for energy leads to massive dig in the desert

Chinese workers take a lunch break at the Sindh Engro
Islamabad - Arab today

n the dusty scrub of the Thar desert, Pakistan has begun to dig up one of the world’s largest deposits of low-grade, brown, dirty coal to fuel new power stations that could revolutionise the country’s economy.

The project is one of the most expensive among an array of ambitious energy developments that China is helping the country to build as part of a $55 billion (Dh200 billion) economic partnership.

A $3.5 billion joint venture between the neighbours will extract coal to generate 1.3 gigawatts of electricity that will be sent across the country on a new $3 billion transmission network.

“When I came it was a mess. There was nothing here,” said Dileep Kumar, one of the first mining engineers at lead contractor Sindh Engro Coal Mining Co, standing atop the mile-wide hole in the earth, busy with yellow trucks and diggers on the floor below. “Now look at it. This wasn’t possible without the Chinese

On paper, Pakistan could be one of Asia’s top economies, with almost 200 million people spread over an area twice the size of California, from the icebound peaks of the Karakorum to the warm, dry shores of the Arabian Sea. But it remains hobbled by corruption, political turmoil, terrorism and poverty, all underpinned by a crippling shortage of energy.

The country has natural gas reserves, four nuclear-power stations and the world’s largest dam. Some 700km north of the Thar mine another Chinese company is helping build a solar farm eight times the size of New York’s Central Park.

Yet power outages remain a way of life with blackouts of 12 hours or more even in Karachi and Islamabad. By one estimate, the shortage of electricity is wiping 2 percentage points off economic growth every year. Thirst for energy is taking Pakistan in the opposite direction of Western countries that are trying to reduce coal power, or use cleaner-burning fuel and technologies. Germany, which still relies on coal-fired stations for two fifths of its electricity, has promised to switch half of them off by 2030.

Import bill

Pakistan by contrast relies on coal for just 0.1 per cent of its power, according to the Pakistan Business Council. The Thar projects and others could see that jump to 24 per cent by 2020, according to Tahir Abbas, analyst at Karachi-based brokerage Arif Habib Ltd.

Pakistan’s coal reserves would give the nation a cheap domestic alternative to expensive oil and gas imports.

The nation spends about $8 billion a year on imported petroleum and is one of the region’s biggest buyers of liquefied natural gas.

In an effort to curb the import bill and meet demand for power, Pakistan plans to dig up some of the world’s biggest known deposits of lignite, a lower-grade brown coal. But first, it must clear 160 metres of sand to get to the coal.

On a flat, arid plain, separated from a hot cerulean sky by a thin line of spindly scrub, yellow-edged containers sit neatly around paved quadrangles. In the centre of each, a lumpy circle of green turf, irrigated by a hosepipe, provides some respite from the dust and heat.

The Spartan accommodation houses about 350 Chinese workers on six-month stints, working 6am to 6pm with a three-hour break during the hottest part of the day, when summer temperatures can reach 42 degrees Celsius.

Nearby, similar compounds house the Pakistani engineers and workers, mostly from Karachi. The two groups keep separate schedules and take separate meals, with the cook turning meat into biryani and curries for one side and dumplings for the other.

A kilometre from the living compounds, a massive square terraced hole is being carved out of the dust. Yellow Chinese dump trucks made by Shaanxi Tonly Heavy Industries Co line up at the bottom to be filled with dirt by hydraulic excavators. Many of the drivers of the fleet of 125 trucks are locals, Hindus and Muslims.

Finally happening

In every cab and cabin are bottles of Nestle mineral water, a precious resource. For everything else the company extracts groundwater.

Engro will reach the coal by the end of 2018, six months earlier than scheduled, Chief Executive Officer Shamsuddin Ahmad Shaikh said in an interview. After decades of delays, the injection of Chinese capital and resources has made investors and companies believe the project will finally happen.

“All the big industrial groups in Pakistan have already asked us to give them coal” for future power plants, said Shaikh.

And this is only the start. Engro has already begun digging a second pit and another Chinese joint venture, Sino-Sindh Resource, and Shanghai Electric Group Co plan to start on a similar coal power project nearby in June. Oracle Coalfields plans coal production and electricity at another block by 2019.

In all, the Thar region could produce enough coal to generate 15 gigawatts within 10 years, Mohammad Younus Dagha, secretary of Pakistan’s Ministry of Water and Power, said

source : gulfnews

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

thirst for energy leads to massive dig in the desert thirst for energy leads to massive dig in the desert

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

thirst for energy leads to massive dig in the desert thirst for energy leads to massive dig in the desert

 



GMT 00:19 2017 Wednesday ,20 September

France's Macron to meet Italian PM on Sunday

GMT 04:41 2015 Monday ,23 March

Kuwait's Wushu-kung fu championship ends

GMT 06:40 2017 Tuesday ,26 September

Palestinian gunman kills three Israelis at settlement

GMT 22:03 2017 Wednesday ,06 September

Pope Francis lands in Colombia to support peace

GMT 10:33 2017 Thursday ,20 April

Smoking to kill 200 million

GMT 02:12 2017 Friday ,14 July

Israel arrests "terror plot" Palestinians

GMT 11:32 2017 Thursday ,13 April

Malala Yousafzai becomes youngest ever

GMT 11:03 2012 Sunday ,05 August

Activist Jamal Al-Amwasi

GMT 13:48 2017 Tuesday ,21 November

Family ends row over legacy of artist Arman

GMT 23:11 2018 Thursday ,11 October

GCC renewable energy discussed in Kuwait

GMT 08:45 2011 Tuesday ,27 September

Tyra beautiful in pink

GMT 08:47 2018 Tuesday ,16 January

Football: Giggs set to be named as Wales boss

GMT 15:03 2011 Tuesday ,19 July

Al-Maliki voted Iran’s worst PM

GMT 08:36 2017 Monday ,25 December

Ashes gone, pride at stake for wounded England
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday