The French government on Sunday published a decree for closing the country’s oldest nuclear plant, fulfilling a campaign-trail pledge made by President Francois Hollande who is now in the final weeks of office.
The decree, gazetted in the Official Journal which publishes government decisions, sets down the conditions for closing a nuclear plant at Fessenheim, near the border with Germany.
Fessenheim will cease operations when a new reactor, currently being built at Flamanville on the Normandy coast, “enters service,” the decree said.
France’s nuclear plant operator EDF last month said the Flamanville reactor — a project that has run into deep problems — will begin operations in 2019.
The closure of the twin-reactor plant at Fessenheim is part of a plan to slash France’s dependence on atomic energy.
Hollande, who leaves office next month, vowed during campaigning in the 2012 election to close the facility as part of a promise to reduce the share of nuclear in the energy mix from 75 percent to 50 percent and boost the share of renewables.
Fessenheim, in operation since 1977, is located on a seismic fault line about 100 kilometers (60 miles) south of Strasbourg.
Its closure has been a campaign target by French, German and Swiss environmentalists for years.
The conservative opposition has opposed the energy program, arguing that France’s nuclear industry is a guarantor of the country’s energy independence and a source of cheap electricity.
The new European Pressurised Reactor (EPR) reactor, being built at Flamanville alongside two existing reactors, is a novel third-generation design touted as the world’s biggest and advanced nuclear reactor.
But the project, along with another EPR contract in Finland, has been plagued by delays and technical problems.
Construction of the reactor began in December 2007, with an operational start initially scheduled for the end of 2012. Costs have tripled to 10.5 billion euros ($11.1 billion).
On March 16, EDF announced that it had begun the test phase of the Flamanville EPR, and this would run until the end of 2018.
The reactor will be hooked up to the national grid in the second quarter of 2019, it said.
Two EPR reactors are scheduled to be built at Hinkley Point in southwestern Britain under a Chinese-backed deal announced last year.
Source: Arab News